Sheet A2.1 — CMU Block Count
Sheets Shop Drawings Book a Demo →
CMU Estimating · Block by Block

CMU estimating: from block count to bid

Fulls, halves, and corners are counted from the first click as you draw your walls. The Masonry Modeler is masonry estimating software that connects the CMU wall you draw to the materials, crews, equipment, and markup in your bid.

Start with the wall and specifications

Wall area is a useful starting check. For nominal 8-by-16-inch CMU, 1.125 units per square foot gives a full-unit equivalent. A purchase list also needs the actual fulls, halves, corners, bond beams, and cuts, plus the specified finishes and allowances.

A corner's position and its purchased unit are related, but the specified block determines what you buy. Smooth 8-inch CMU may use regular stock at a corner; textured units or other widths can need special units. Review the corners, openings, control joints, and non-modular heights before pricing.

Square-footage method

What you get

  • One number: total blocks
  • Corners buried in waste factor
  • Bond beams estimated, not scheduled
  • Half-highs invisible until the job
  • Cuts absorbed into rounding
TMM block-by-block

What you get

The 88th Avenue Pump Station

Real job. Real numbers. The 88th Avenue pump station has a 280 linear foot perimeter broken into 12 wall segments. Rakes, a door, bond beam courses, non-modular height at the parapet.

Tracing it in TMM took 3.7 minutes. The block count came out automatically — not a square-footage estimate adjusted upward, but a rendered wall with every unit in its position.

280 lf Wall perimeter
12 Wall segments
3.7 min Blank canvas → takeoff
88th Ave pump station · traced in TMM · all numbers confirmed
Pump Station · trace → takeoff · 3 min Powder River Masonry · MasonX

The takeoff separated stretchers, corner blocks, bond beam units, and the half-high parapet course. Not estimated. Counted.

And the same model labels the wall: that block count travels straight onto the masonry shop drawings, course by course.

How to prepare a masonry estimate

  1. Define the scope. Read the plans and specifications. Set wall lengths, heights, thicknesses, finishes, openings, and reinforcement.
  2. Review the takeoff. Check the fulls, halves, specialty units, cuts, mortar, grout, and reinforcing. Account for accessories and job-specific allowances.
  3. Apply your costs. Use supplier quotes, mortar coverage, grout pricing, loaded labor costs, and equipment rates. Check delivery, minimum orders, waste, and tax.
  4. Price how you will build. Set production rates and the working crew. Review the days for laying and grouting, plus access and other work.
  5. Review the bid. Add overhead and profit, resolve missing scope or rates, and compare the estimate to the plans before sending it.

The masonry estimating software overview shows how the count connects to the bid. Below is one small worked example with all its assumptions visible.

Worked example · sample rates

One CMU wall, priced all the way through.

A simple 20 × 8 ft wall in 8-inch CMU. Start with the units in the wall, then add the crew and equipment it takes to lay them.

160 sq ft of wall 174 full + 12 half = 186 pieces 1.5 CY grout 6 mortar bags

Materials $1,086.00

Fully grouted example: 360 cells ÷ a sample yield of 240 cells/CY = 1.5 CY.

Mortar: 186 laid pieces ÷ a sample coverage of 31 pieces/bag = 6 bags.

Full 8-inch CMU 174 blocks × $3.33/block
$579.42
Factory half CMU 12 blocks × $2.22/block
$26.64
Grout 1.5 CY × $300.00/CY
$450.00
Mortar 6 bags × $4.99/bag
$29.94

Labor $320.00

1 mason × 8 hours/day × $20.00/hour. Production rates: 186 pieces and 1.5 CY per mason-day, one day each. Sample wage only; use your full crew cost, including helpers and payroll burden.

Lay block1 mason-day
$160.00
Grout wall1 mason-day
$160.00

Equipment $20.00

Day-only mixer2 days × $10.00/day
$20.00
Direct cost$1,426.00
Overhead · 10% of cost$142.60
Profit · 10% of cost plus overhead$156.86
Sample bid$1,725.46
Block count questions

What the foreman always asks.

How do I turn a CMU block count into an estimate?

Price the fulls, halves, and specialty units, then add mortar, grout, reinforcing, and accessories. Apply your production rates, crew labor, and equipment costs. Review allowances, tax, overhead, and profit against the project scope before issuing the bid.

Why is a block-by-block count more accurate than square footage?

Square-footage takeoffs apply a factor — typically 1.125 blocks per square foot — then round up. That factor doesn't know about corners, openings, bond beams, or non-modular heights. Block-by-block counts each unit type individually, so the order matches what the crew actually lays.

What does "non-modular" mean and why does it matter?

Non-modular means a dimension does not land on the selected unit module. A remaining height may need a specified half-high unit or a cut from full-height stock. Review both the placed piece and the unit you need to purchase.

How long does it take to trace a building and get a block count?

The 88th Avenue pump station — 280 linear feet of perimeter, 12 wall segments — took 3.7 minutes from blank canvas to a full block-by-block takeoff. Larger projects take proportionally longer, but the tracing step is fast because it counts as you draw.

What block types does TMM count separately?

Standard stretchers, corner blocks (inside and outside), bond beam units, lintel units, half-high blocks, sill blocks, and cut pieces at non-modular wall ends. Review the placed piece types and their purchased units separately from any waste allowance.

Count every block before the order goes in.